Enter the award, the budget by category and what has been spent each month. The dashboard compares money spent with time gone, carries the recent pace to the end of the period, and tells you what a month of spending has to look like to use the award, with the closeout dates that follow.
Included with Caveat Classroom and Whole-school licenses. Or get it in the Grant writer’s desk, $49 for 32 items.
The worked example is made up: a $360,000 first-year award, October to September, with books through April. Change any figure or start blank. Nothing you enter leaves this browser.
Loading the dashboard. If nothing appears, turn on JavaScript.
One row per budget category. Steady categories are projected straight-line from the average month so far; one-time categories (equipment bought once, a single contract) are held at spent plus committed.
Spending posted in each month, from the start of the period to the month the books are reported through. The total should match the spent column on Categories.
Advancement · Grants & Funding$19 · included with Classroom and Whole-school licenses
Arithmetic on your own figures, with the federal closeout dates in general terms.
The burn ratio divides the share of the award spent by the share of the budget period gone. Near 1.0, spending is keeping time; well under 1.0 means money is likely to be left at the end; over 1.0 means it may run out early. The page flags under 0.85 and over 1.15 as its own rule of thumb.
Two projections carry spending to the end: the average of the last three months, which reflects where a program is now, and the average month since the start. Neither is allowed below what is already spent plus what is committed. Each category is projected straight-line from its own average month unless you mark it one-time, when it is held at spent plus committed.
Under the Uniform Guidance for federal awards (2 CFR 200), a cost is allowable only if it is incurred during the approved budget period, and at closeout a recipient must liquidate all obligations incurred under the award no later than 120 calendar days after the end of the period of performance, unless the agency authorizes an extension. Agencies may restrict transfers among direct cost categories without prior approval once the cumulative transfers exceed 10 percent of the last approved budget on awards whose federal share exceeds the simplified acquisition threshold. Foundations, state awards and subawards set their own terms; the award document governs.
The worked example is made up. The forecast is arithmetic on the figures you enter and is not an accounting record or legal advice. The federal rules are described in general terms; the terms of each award, your funder and your organization’s policies decide what applies. Your figures stay in this browser. Support: team@caveatacademic.com.